Progress Update!
December 12, 2012
Significant progress is being made on four of the five buildings for the Student Residences Project.
Building #1 already has the second floor framed in, while the first floors have begun on Building #2. Foundations for Building #3 will be poured this week. Underground plumbing and electrical for Building #4 should also be completed this week.