Smooth and steady progress
March 08, 2013
Work crews continue their progress on the new residences.
At the Student Residences Project, insulators worked all week getting the walls ready for drywall in Building 1B. In Building 1C, the electricians did their rough work and started layout for Building 2. Building 2 also had sprinkler pipe, windows and roofing material installed this week. The framers were excited to finish up Building 1C this week, which will now begin to be waterproofed. The plumbers worked hard on the underground for the final building, which is now ready for slab preparations. The final building’s slab placement is scheduled for Wednesday of next week.
